Noida-Delhi Journey Will Be Pleasant, Barapula Phase-3 Will Be Ready in October

 
Noida-Delhi Journey Will Be Pleasant, Barapula Phase-3 Will Be Ready in October

Barapula Phase 3: There is a big good news for the people of Delhi. This year the journey from AIIMS to Mayur Vihar will become easier. Barapula Phase 3 Corridor is intended to be completed by October. The obstacles to this scheme that have been running for six years have now been removed.

Barapula Phase 3

Construction of Barapula Phase 3 began in 2015 and was scheduled to be completed by 2017, but work was delayed due to lack of land. To complete the project quickly, two acres of land has recently been acquired with the help of LG.

Read More - Now Vande Bharat Train Will Not Leave For UP, Know New Update of Railways

Telegram Link Join Now Join Now

land acquisition

The foundation stone of Barapula Phase 3 in East Delhi was laid in 2014 and it was to be completed in three years. But due to shortage of 2779.09 square meter land in Nangli Raza village, the scheme was stalled for six years. Last November, LG had the courage to complain loudly about the delays.

Read More - Bajaj Pulsar N250 Bike With Cool Features Launched, Know its Price, Engine, Mileage & Features Details

benefit to the public

Supporting Barapula Phase 3 will ease the journey from Mayur Vihar to Sarai Kale Khan. Mayur Vihar will also provide a new route from Noida to South Delhi. Along with improving the traffic system of Delhi, it will help people in saving time and energy.